Sunday, December 12, 2010

Press in Port at Baltimore harbor!



Press in Baltimore Port

Blog for Miraflex at Bema, Inc.

Bema Endeavor Blog for Miraflex

Concrete work and area ready for the Miraflex





The press is 3 days away from coming through the doors at Bema. Then the process of installing, testing and debugging the press begins. This process should take approximately 45 days. That being the case, the press should be up and running by mid-February.
The last time Bema installed the  W& H , 10 color Primaflex, the process went smoothly and was running product 2 days after commissioning. Based on prior experience with W&H equipment , we are anticipating the same with the W&H 8 color Miraflex press.
 More to come as the press arrives!

Monday, December 6, 2010

More headway at Bema, Inc. for the Miraflex press!

Gerry's handiwork!

Equipment for the Miraflex.

The entire area that will be occupied by the Miraflex.